Scrum Notes 1/23/16

Team Field Elements

  • Port de Cullis: Nearly done. Figured out how to counter weight. Need to get a counterweight mass of appropriate size. Will be done today.
  • Low Bar: Needs supports on the ramp. Will be done today
  • Painting: Everything built is done. Castle wall is done. Waiting on Port Cullis.

 

Team Prototyping

Design A – Catapult

  • Let’s try w/ quadrupled surgical hose instead.
  • Need to mount it steel bar rack.

Design B – Fly Wheel

  • Will test today. Done otherwise. Needs to be smaller.

Design C – Picker-Upper box

  • Sprinkler hose tubing into 2 in. pieces. Worked a lot better
  • Secured the center w/ zip ties
  • Ball goes back into center even from the side
  • Added handles.
  • Need make side bumpers.

 

Team Chassis

  • Full scale cardboard model of the center cross member. Continue to work
  • Axles in the gear box need to be cut, tapped, and drilled (half are drilled. none are tapped. will try to finish today)
  • Cutting steering knuckles. Need to be drilled. Will continue to drill.
  • Need to make roll bar. Use welding (SUNDAY 12~1 Jason, Jane, Kate, and Ed)

 

——————————————————————————————

 

Team Field Elements

  • Low Bar: DONE
  • Port de Cullis: Donald?
  • Painting: Working on drawbridge, everything built is done except on drawbridge

 

Team Prototyping

Design A

  • Added springs instead of surgical hose
  • Will test later today

Design B – Fly Wheel

  • found all the parts. Should be operational. Wrote some code
  • Will test later today!

Design C – Picker-Upper box

  • changed EMT to sprinkler hose
  • need trim and secure the center.
  • Will keep on testing. Getting ball back up to the center

 

Team Chassis

  • Full scale cardboard model of the center cross member. Will finish today.

 

Team Clean Up

  • Room is basically clean except for backwall (we will do next week?)
  • Table is COMPLETELY clean. Goals.