Team Field Elements
- Port de Cullis: Nearly done. Figured out how to counter weight. Need to get a counterweight mass of appropriate size. Will be done today.
 - Low Bar: Needs supports on the ramp. Will be done today
 - Painting: Everything built is done. Castle wall is done. Waiting on Port Cullis.
 
Team Prototyping
Design A – Catapult
- Let’s try w/ quadrupled surgical hose instead.
 - Need to mount it steel bar rack.
 
Design B – Fly Wheel
- Will test today. Done otherwise. Needs to be smaller.
 
Design C – Picker-Upper box
- Sprinkler hose tubing into 2 in. pieces. Worked a lot better
 - Secured the center w/ zip ties
 - Ball goes back into center even from the side
 - Added handles.
 - Need make side bumpers.
 
Team Chassis
- Full scale cardboard model of the center cross member. Continue to work
 - Axles in the gear box need to be cut, tapped, and drilled (half are drilled. none are tapped. will try to finish today)
 - Cutting steering knuckles. Need to be drilled. Will continue to drill.
 - Need to make roll bar. Use welding (SUNDAY 12~1 Jason, Jane, Kate, and Ed)
 
——————————————————————————————
Team Field Elements
- Low Bar: DONE
 - Port de Cullis: Donald?
 - Painting: Working on drawbridge, everything built is done except on drawbridge
 
Team Prototyping
Design A
- Added springs instead of surgical hose
 - Will test later today
 
Design B – Fly Wheel
- found all the parts. Should be operational. Wrote some code
 - Will test later today!
 
Design C – Picker-Upper box
- changed EMT to sprinkler hose
 - need trim and secure the center.
 - Will keep on testing. Getting ball back up to the center
 
Team Chassis
- Full scale cardboard model of the center cross member. Will finish today.
 
Team Clean Up
- Room is basically clean except for backwall (we will do next week?)
 - Table is COMPLETELY clean. Goals.
 